When should a Korean OEM contract treat a shipment as accepted?

4 min read
In this article

The short answer

Treat delivery, inspection, acceptance and continuing warranty obligations as separate events. An OEM contract should identify the agreed product specification, the tests that establish conformity, who performs them and how defects are reported and remedied. First check whether the Korean subcontracting regime covers the transaction: mandatory inspection and payment protections may constrain the proposed terms. A negotiated acceptance procedure is useful, but it is not a licence to postpone payment indefinitely or erase every later defect claim.

[1] [2]

Start with the specification that testing will actually measure

A purchase order saying “same as approved sample” can conceal a difficult question: which characteristics of the sample are binding? Identify dimensions, materials, performance tolerances and packaging, together with the version of each drawing. Distinguish customer design requirements from manufacturing choices entrusted to the supplier. That distinction helps explain whether a failure reflects an unsuitable design or a departure from agreed production instructions.

Make the documents work together. A master agreement, order, quality manual and engineering email should not each have an unexplained claim to priority. Specify who may approve a change, how its cost and delivery effects are recorded, and whether another test run is needed. These are practical evidence controls, not a substitute for statutory written terms where subcontracting legislation applies.

[1] [2]

Check whether the proposed inspection process is legally available

The Fair Transactions in Subcontracting Act can regulate covered manufacturing entrustments, including written documentation, inspection, payment and unfair conduct. Coverage depends on the parties and entrusted activity, rather than an OEM heading or the buyer’s preferred governing-law clause. Gather the relevant business and transaction information before adopting a global supplier template.

Do not begin with an arbitrary acceptance period borrowed from another country. Compare the proposed inspection and rejection mechanics with the applicable Korean requirements, including relevant conditions and exceptions. A commercial desire to await the buyer’s own customer approval may not justify shifting that entire uncertainty to the manufacturer. Review the inspection and payment provisions together rather than treating them as independent negotiations.

[2]

Create usable evidence at each handover

Define whether testing occurs at the factory, at destination or in both places, and identify the result each test establishes. Receipt records can show quantities and apparent transit damage without proving performance under operating conditions. Sampling may be efficient, but the agreement should explain what a failed sample means for the remaining batch and how disputed results are checked.

A rejection notice should identify the affected units, the requirement not met and the available supporting records. Consider sample preservation, access to inspect and a route for repeat testing when the parties disagree. These arrangements make a cure decision possible. They should not be drafted as a procedural trap that purports to remove rights which mandatory law preserves.

[1] [2]

Keep acceptance distinct from warranty and production exit

A product can pass the agreed inspection and later reveal a concealed defect. Explain which warranty obligations continue after acceptance, how repair or replacement will work, and who investigates competing causes. Avoid describing every later malfunction as automatically the supplier’s fault: storage, installation, customer modifications and the agreed design may matter to causation and responsibility.

The process also needs an answer when replacement is impractical. Address rejected stock, unused dedicated materials, tooling access and the evidence needed for claimed losses. Separate ordinary correction costs from broader interruption or recall exposure. If demand changes rather than quality fails, use the ordering and change-control provisions instead of manufacturing a quality rejection to escape a purchasing commitment.

[1] [2]

Illustrative example

In this hypothetical scenario, an overseas buyer approves a prototype and orders a production batch from a Korean manufacturer. The batch passes dimensional testing but fails after installation in a hotter environment. If the operating temperature was part of the agreed specification, the supplier’s conformity and warranty obligations become central. If it was never communicated and the buyer selected the design, responsibility may look different. The acceptance record helps establish what was tested; it does not independently decide the cause of failure or extinguish applicable statutory rights.

What to prepare before seeking advice

  • Collect the approved sample record and dated specification versions.
  • Identify the buyer, manufacturer and entrusted production activity.
  • Map factory, delivery and operational tests to their decision owners.
  • Prepare batch records and a proposed defect-notification workflow.
  • List dedicated tooling, unused materials and replacement constraints.

Common questions

Can our customer’s approval be the only acceptance test?

It may be commercially relevant, but it needs a defined relationship to the supplier’s obligations. An open-ended approval condition can leave payment and rejection uncertain. Check the subcontracting regime and the objective product requirements before making a third party’s decision the sole trigger. [1] [2]

Does accepting delivery waive later defect claims?

Not necessarily. Receipt, contractual acceptance and continuing defect remedies are different questions. The agreed terms, nature of the defect, inspection evidence and applicable mandatory protections matter. Draft the continuing obligations expressly rather than assuming a signed delivery receipt settles all future quality issues. [1] [2]

Official sources and version notes

Source verification dates are shown separately from article preparation. Korean controlling text and the rules applicable to the relevant date take priority over reference translations.

  1. Civil Act

    Korea Legislation Research Institute · English reference translation · Source checked 2026-11-23

    Source scope and version
    • Contract performance, damages, lease preservation and expenses, inheritance opening and succession framework.
    • Inspected official publication. Korean controlling text and applicable commencement provisions prevail; English translation currency is not certified. Workflow and document suggestions are practical analysis, not universal statutory requirements.
  2. Fair Transactions in Subcontracting Act

    Korea Legislation Research Institute · English reference translation · Source checked 2026-11-23

    Source scope and version
    • Covered manufacturing/service entrustments; written orders and changes, inspection, payment, technical data and raw-material price adjustment.
    • Inspected official publication. Korean controlling text and applicable commencement provisions prevail; English translation currency is not certified. Workflow and document suggestions are practical analysis, not universal statutory requirements.

General legal information, not advice or a determination for a particular matter. Check current Korean law and applicable commencement provisions before acting.